| 2.1
General policies, plans & funding |
top |
2.1.1
Czech Republic: In January 2000, the three Czech repositories
were transferred to state ownership ahead of the summer deadline
that had been stipulated in the new atomic law. The three
sites are: the Dukovany surface repository for low-level radioactive
waste; the Bratrstvi mine complex; Jachymov near Litomerice,
for LLW and ILW. The new atomic law also led to the established
of the radioactive waste repository authority (RAWRA).
2.1.2 France: In March, OPECST, the parliamentary commission
for the assessment of scientific and technological
options, fully endorsed the recommendations from MP Michèle
Rivasi's report entitled The consequences of nuclear waste
storage facilities for human health and the environment.
The report recommends twelve different measures including:
- Increasing
research and development in order to reduce radioactive
discharges, ahead of the 2020 OSPAR deadline, to levels
close to zero for artificial radionuclides and near to background
levels for naturally occurring radionuclides.
- Investigating
the possibility to grant discharge permits with the ultimate
objective of achieving lower discharges.
- Involving
the health ministry with any procedure or authorisation
process concerning radioactive waste management.
2.1.3 Germany: Waste management issues are included in
the federal government's plan to phase out nuclear
energy and include the following:
Interim
storage: utilities will be building interim storage facilities
as soon as possible at, or close to, reactor sites. Utilities
expect that it will be some five years before they have interim
storage sites available to them and in the meantime they will
arrange on-site temporary storage.
Transport:
utilities are permitted to transport spent fuel to the centralised
storage facilities, Gorleben and Arhaus, until such time that
on-site facilities are available. International transports
are also permitted until all reprocessing contracts have been
met.
Gorleben:
exploration works of the salt dome have been suspended for
three to ten years during which time further clarification
of technical, conceptual and safety issues are made. The federal
government affirms its commitment to fully assume legal responsibility
for establishing the disposal installations in due time irrespective
of the nuclear phase out. Salt, granite, clay and other geological
formations will all be considered. Some questions have been
raised concerning the research on the Gorleben site, including:
- Overpressure
from gas build-up in dense rock salt.
- Public
pressure to provide a retrievability option.
- Lack
of comparison to other geological formations.
- Additional
safety requirements to prevent delayed criticality.
Pilot
Conditioning Plant (PKA): the responsible authorities
will conclude the approval process; however, the works will
be limited to repairing casks.
Konrad
mine shaft for LILW disposal: responsible authorities
will conclude the approval process.
2.1.4
Italy: In December 1999, the government outlined plans
for nuclear decommissioning and the associated waste management
programmes. Three main goals were defined:
- All
onsite radioactive waste should be treated and conditioned
within the next ten years with the view to subsequent transport
to a national repository.
- Site
selection and construction of a national repository for
the disposal of LLW and ILW should be accomplished within
ten years. The site should also be suitable for the interim
storage of long-lived LLW, ILW and spent fuel, plus residues
from former reprocessed fuel.
- Decommissioning
of NPPs, with a view to returning the sites to green field
status, should be achieved within the next twenty years.
The
recently created subsidiary from ENEL (the responsible authority
for radioactive waste management in Italy), SOGIN, will be
responsible for implementing the plan. Funding (approximately
6000 billion lire (US$2.9 billion) plus 50 billion lire (US$20
million) - per year in management costs) will come partly
from the ENEL decommissioning reserve and partly from a special
'nuclear component' of the electricity pricing system.
2.1.5 Slovakia: The government launched a new radioactive
waste management programme in March 2000 that proposes
the creation of a new waste treatment centre and national
repository. Construction of the Bohunice waste treatment and
conditioning centre started in 1993. It will process wastes
from the decommissioning of A-1 Bohunice NPP, operational
wastes from two of the four Bohunice VVERs, and institutional
wastes. The redesigned Mochovce national repository could
also provide new disposal facilities subject to a peer review
of the IAEA under the Waste Management Assessment and Technical
Review Programme (WATRP).
2.1.6 Spain and Slovenia: ENRESA, the Spanish national
waste agency is assisting the Slovenian waste agency, RAO,
with the development and management of a LILW repository in
Slovenia. ENRESA manage El Cabril, which receives institutional
waste from the medical industry as well as the nuclear power
sector.
2.1.7 Spain: A new waste plan, approved by the government
at the end of July 1999, delays any decisions about long-term
high-level waste management until at least 2010. The plan,
proposed by state-owned radwaste company ENRESA, leaves all
options open for the future management of spent fuel from
Spanish nuclear power plants. A further 10 years will be spent
on research and development before a decision is made.
2.1.8
Switzerland:
Early in March 2000, a draft revision of the Atomic Law (Kernenergiegesetz)
was submitted for comment to the stakeholder groups: the public,
political parties, industry and anti-nuclear groups. The main
purpose for the review was to clarify the institutional role
of the federal and cantonal governments in the licensing of
repositories for radioactive waste. The federal government
used the revised law to instigate discussion on a number of
fundamental issues concerning the future of nuclear power
in Switzerland. It invited comment on a number of areas including:
- Should
nuclear power remain an option for future electricity production
in Switzerland?
- Should
the operating life of existing power plants in Switzerland
be time limited?
- Should
the recently developed concept for the geological disposal
of radioactive waste (after an extended period of observation)
be pursued?
- Should
the reprocessing of Swiss spent fuel continue?
- Should
the law provide full public consultation prior to the initiation
of a radioactive waste disposal programme?
The
consultation period ended in mid-June 2000 and it is expected
that the revised law will become effective during 2001.
A
new administrative order requires utilities to set aside funds
over the next five years to cover the future costs of management
and disposal of the spent fuel from decommissioned power plants.
Such funds already exist, dating back to the start-up time
of the power plants, but up to now the funds may have been
used for other projects. Now they are segregated and controlled
by the central government on a plant-specific basis.
2.1.9 UK: In response to the 1999 House of Lords select
committee report on the management of nuclear waste, UK environment
Minister, Michael Meacher, announced widespread government
consultation on the issue. The Minister stressed the government's
commitment to a fully comprehensive policy for managing long-lived
nuclear waste. The intention is for this policy to be developed
in a transparent and open-minded way to ensure maximum public
acceptance before decisions are made whether to continue storage
above ground, or to initiate further research into deep underground
disposal. The next stage of the proceedings will include the
publication of a detailed and wide-ranging consultation paper
discussing the processes involved for the implementation of
the various radioactive waste management options. The latest
radioactive waste inventory for the UK reports a 17% decrease
in the forecast of total conditioned HLW and a 26% decrease
in the forecast for ILW.
2.1.10 USA: American utilities remain dissatisfied with
the US Senate dealing of the nuclear waste bill, S-1287. The
veto on the bill was sustained following a vote in the Senate
on 2 May 2000 where ninety-nine Senators voted at 64-35. The
bill requires a two-thirds majority for it to be passed.
The
waste bill will permit the final disposal of spent fuel to
Nevada's Yucca Mountain. The public hearing on the Yucca Mountain
environmental impact assessment ended on 28 February. It is
expected that the Secretary of Energy will decided whether
to recommend Yucca Mountain to the President as the repository
for highly radioactive nuclear waste in 2001.
| 2.2
Low & intermediate waste treatment |
top |
2.2.1 Canada: Construction approval was given by AECB
for the modular aboveground storage (MAGS), at Chalk River
Laboratories, on 19 November 1999 and the C$3 million (US$1.3
million) project started on 5 January 2000. The system will
include a super-compactor to reduce the total volume of waste
by a factor of twenty. Low-level wastes will be sorted, compacted,
and packaged in metal containers (either conventional steel
drums or purpose built steel boxes approximately 1x1x2 m).
A maximum of ten storage buildings will be built each with
a capacity to store up to two years of low-level waste generated
both locally and elsewhere in Canada.
2.2.2 Switzerland: The final operating license for ZWILAG
LLW incineration and conditioning unit was granted in March
2000.
2.2.3 UK: The Environment Agency (EA) has given permission
for LLW from the former Brent Spar offshore oil installation
to be brought to Britain from Norway for treatment. The Agency
has authorised the import of three drums of low specific activity
(LSA) waste from the decommissioned oil platform, which will
be evaluated by AEA Technology. The company then intends to
apply for permission to process the remaining several hundred
drums of sludge, scale and rock after the evaluation process.
The waste is natural radioactive material resulting from drilling
and production, and will be used to test processing methods
at AEA's Winfrith plant in Dorset, UK. The waste will then
be sent to BNFL's Drigg disposal site for long-term disposal.
2.2.4
USA: In March, the US Energy Secretary, Richardson, announced
that the US administration had dropped a project for
the construction of an incineration plant in Wyoming, following
environmental opposition. BNFL was awarded the contract to
compact and incinerate wastes from Idaho National Engineering
and Environmental Laboratory (INEEL).
ATG
Inc. has received the authorisation to construct and operate
the country's first commercial mixed waste facility
at its Richland centre (Washington). The permit allows ATG
to treat commercial and government-generated LLW that also
contain hazardous chemical contamination.
| 2.3
Low & intermediate waste disposal |
top |
2.3.1
Switzerland: ZWILAG, the national intermediate storage
facility at Würenlingen, opened for operation on 1 January
2000 having obtained all necessary operating licences, including
a licence for the operation of its high temperature plasma
furnace. The furnace will convert many sources of low and
intermediate level waste into a stable glass-like material
suited for permanent disposal.
ZWILAG
is owned by the nuclear utilities in Switzerland who have
recently decided to add to the existing storage facilities
(currently for spent fuel and high-level and medium-level
waste) a storage hall for low-level waste. With this addition,
the ZWILAG facility, together with the smaller, intermediate
storage facility ZWIBEZ at the Beznau reactor site, will be
able to store all radioactive waste from the five operating
reactors in Switzerland for up to fifty years operation plus
wastes arising from decommissioning.
| 2.4
Transuranic waste disposal |
top |
2.4.1 USA: The final Resource Conservation & Recovery
Act (RCRA) permit for the disposal of low-level transuranic
and hazardous chemical wastes at the US Department of Energy
Waste Isolation Pilot Plant (WIPP) was granted from the state
of New Mexico in October 1999.
| 2.5
Spent fuel & high level waste interim storage |
top
|
2.5.1
Canada: On 20 January 2000, the Atomic Energy Control
Board (AECB) of Canada approved the construction proposal
for a used fuel dry storage facility at the Bruce Nuclear
Power development, submitted by Ontario Power Generation (OPG).
The current approval is for the construction phase. The future
operation of the facility will require additional application
to AECB.
2.5.2 Czech Republic: The central interim storage facility
for spent nuclear fuel at Dukovany plant proceeded as planned
in December 1999. The regulatory body licensed the use of
the new Skoda 440/84 cask and permitted CEZ, the operator,
to expand storage capacity.
2.5.3 Germany: During December 1999, nine new applications
for on-site interim storage at nuclear power plants were submitted
to the government. The applications came from Brokdorf, Unterweser,
Stade, Grohnde, Krümmel, Brunsbüttel, Neckarwestheim,
Phillippsburg and Biblis NPPs. Further applications are expected,
while spent fuel transport restrictions remain in place.
2.5.4 Russia: In early 2000, the new authorities announced
that they are considering the development of a spent fuel
storage facility on the Kola Peninsula to provide safe storage
of 60 000 spent fuel elements from nuclear submarines, currently
stored in the Murmansk region. SKB, the Swedish Nuclear Fuel
and Waste Management Company, welcomed this decision.
2.5.5
Spain:
Preparation for a spent fuel storage facility at the Trillo
reactor site restarted in August 1999 following a government
order. Progress has been delayed due to opposition from the
local community, who fear that the facility would become a
central storage facility for Spain's spent fuel.
2.5.6 USA: In December 1999, the US NRC accepted the proposal
from Private Fuel Storage (PFS), a consortium of eight utilities,
to establish a spent fuel storage facility on Goshute tribal
land, Utah. The go-ahead came following PFS's submission of
their safety evaluation report for the project, which they
consider necessary until the US DOE can allow the fuel to
be moved to a permanent burial ground such as the Yucca Mountain
site in Nevada. The draft environmental impact statement (EIS)
met the approval of the Nuclear Regulatory Commission, the
Bureau of Indian Affairs, the Bureau of Land Management, and
the Surface Transportation Board. The final EIS is scheduled
for completion in February 2001.
| 2.6
Spent fuel & high level waste disposal |
top
|
2.6.1
Germany: an international team of experts declared that
there was no reason that the Gorleben mine cannot meet all
necessary criteria for the safe, long-term storage of spent
fuel. The team was commissioned in December 1999 by the nuclear
utilities to assess the results from the Gorleben salt dome
site investigations. The preliminary responses from the team
of experts are in contradiction to the position of the environment
minister, Mr Trittin, who called for a moratorium on the works
at Gorleben on 22 February 2000, and established a commission
to define permanent disposal criteria. The team of experts
will submit their final report by the end of 2000.
2.6.2 Japan: On 16 May, a plenary session of the Lower
House passed a bill that provides a framework for the final
disposal of high-level radioactive waste and sent it to the
Upper House. The Upper House Committee on Economy and Industry
took up the bill on 17 May. The bill requires consultation
with prefecture governors and heads of local municipalities
when preliminary studies of the proposed sites are made. In
addition, the new law calls for the creation of an organisation
responsible for HLW management.
2.7.1 Belgium: ONDRAS/NIRAS is preparing the second safety
assessment and feasibility interim report for the disposal
of HLW in clay research programme. The completed report will
be issued in late 2000. The federal authority then intends
to submit the report to an international peer review committee
organised by OECD/NEA.
2.7.2 Finland: Both the Finnish Ministry of Trade and
Industry (KTM) and the Nuclear Safety Authority (STUK) approved
the environmental impact assessment (EIA) for the final disposal
of spent fuel from Loviisa and Olkiluoto at Eurojoki on the
Olkiluoto site. The Eurojoki municipality supports the application
and the next stage requires a decision in principle from the
Finnish Council of State, which is necessary prior to the
development of an underground laboratory. The government is
expected to confirm that Eurojoki will get the spent fuel
repository site and construction should commence around 2010,
with authorisation for commissioning around 2020.
2.7.3 France: In May 2000, the government decided to postpone
the site selection for a suitable granite research site for
a spent fuel repository.
2.8.1 Germany: Authorisations for domestic transport to
Ahaus were issued in February 2000 to Neckarwestheim NPP and
Phillippsburg NPP where spent fuel casks are already loaded.
The transport of these casks is not expected before October
2000. Transporting nuclear materials outside national boundaries
remains prohibited.
2.8.2 Switzerland: In summer, 1998, following the French
surface contamination incident of a spent fuel consignment
from the EDF's Bugey power plant, the Swiss licensing authority
banned the transports of spent fuel. The ban was lifted
in the summer 1999 and since then ten shipments of spent fuel
to the La Hague reprocessing facility have occurred.
2.9.1 Norway: Towards the end of 1999, the Norwegian Radiation
Protection Authority commissioned the Institute for Energy
Technology to submit a plan for the removal of contaminated
sediments from the Nitelva River. The radioactive discharges
originate from the Institute of Energy Technology's Kjeller
facility. The bulk of the contamination derives from a reprocessing
facility that operated at Kjeller in the 1950's and 1960's.
The plan should include provisions for the transfer of the
waste to the Himdalen LLW/ILW disposal site before 2001.
2.9.2
UK:
The UK Environment Agency (EA) has announced that it will
introduce revised limits for five main radionuclides that
are discharged from BNFL's Sellafield site. The Agency says
the limits will result in a 'significant' reduction in the
overall permitted discharge levels for tritium, carbon-14,
technetium-99, ruthenium-106 and iodine-129. BNFL says the
announcement followed three years of review and consultation
by the agency and other government departments. BNFL will
work within the new limits, but they will place 'restrictions'
on its operational flexibility and could affect ongoing programmes,
including the cleaning up of historic wastes. The review of
discharges is an important element in the UK's efforts to
achieve the objectives of the OSPAR Strategy with Regard to
Radioactive Wastes.
previous
section / top / next
section
|